Client Teck – Minera Quebrada Blanca
Ubicación Geográfica Región de Tarapaca, Chile
Date 2018-2019
Plant capacity 16.000 habitantes equivalentes (7 plantas)
Solution Wastewater treatment

Wastewater Treatment

In the context of the implementation of the Quebrada Blanca Phase II mining project, 7 wastewater treatment plants were designed to meet the needs of the different work fronts, these being: Mine area, tailings deposit, construction of impulsion line and in the port. In total, 7 treatment plants were designed and supplied for different capacities.

The solution designed for each plant includes the treatment of sewage and the equipment for dehydration and/or disposal of the generated sludge.

The scope of the project includes: development of the detailed engineering of all specialties, supply of all the equipment and elements required for the assembly of the plants and the assembly and commissioning supervision service.